Project Summary - textSectionComponent

Project Summary

With only 2 days to prepare the O2 Arena for this major gymnastic event and 1 day to de-rig it, a team of 68 crew worked a total of 440 hours to build and de-rig an elevated platform for competitors to showcase their incredible skills.

With 20 crew poised and ready to get going on day one, 4 Forklift operators went about unloading the 6 artic lorries. They contained the raised flooring and gymnastic equipment including; sprung floor and mats, pommel horse, rings, vault, parallel bars, horizontal bar, uneven bars, beam, springboards and chalk bowl stands. Construction of the raised platform began. The decks were then clamped together and braced by 400KG weights in numerous positions to ensure that the gymnasts are the only things flying during the competition!

A total of 642 decks, over 3800 clamps and approximately 8 tonnes of weights were used to create, brace and secure the raised platform in readiness for the gymnastic equipment. Rolls of coloured carpet were delivered next; these would cover both the raised platform and the outer surrounding floor. Work continued into the second day with now 22 crew on site to apply the finishing touches to the build.

After a successful tournament, 26 crew set about dismantling the equipment. Exceeding expectations, the crew were able to de-rig and load all trucks two hours ahead of schedule. Generous as we are, we were happy to give the drivers a head start to the next competition at the Echo Arena in Liverpool, where our Northern Crew were standing by for the next build.

Results

68 Crew used. 4 Forklift operators. More than 440hrs worked. 642 decks delivered, unloaded and assembled. Over 3800 clamps used. 8 tonnes of weights positioned to brace the floor. 2 hours saved by client.

Case Study - textSectionComponent

Full steam ahead

With 20 crew poised and ready to get going on day one, 4 Fork Lift operators went about unloading the 6 artic lorries. They contained the raised flooring and gymnastic equipment including; sprung floor and mats, pommel horse, rings, vault, parallel bars, horizontal bar, uneven bars, beam, springboards and chalk bowl stands. Unloading each artic individually, the operators first delivered the flooring into the main arena for the awaiting crew to begin constructing the raised floor.

Gymnastics build - mediaGalleryComponent
Case study 2 - textSectionComponent

As stacks of flooring started to arrive in the main arena, construction of the raised platform began. With floor plans at the ready, our crew began to build the decks, attach the legs and position them where needed.

Crew Meeting - imageComponent
Space - textSectionComponent

                                       

Crew Slide Show - mediaGalleryComponent
Case Study 3 - textSectionComponent

The decks were then clamped together and braced by 400KG weights in numerous positions to ensure that the gymnasts are the only things flying during the competition!

Weights and bracing - mediaGalleryComponent
Case study 4 - textSectionComponent

A total of 642 decks, over 3800 clamps and approximately 8 tonnes of weights were used to create, brace and secure the raised platform in readiness for the gymnastic equipment. Rolls of coloured carpet were delivered next, these would cover both the raised platform and the outer surrounding floor.

Finish Line - sliderComponent
Finish line in sight - textSectionComponent

Work continued into the second day with now 22 crew on site to apply the finishing touches to the build. With the floor in place, carpets laid and equipment tested the competition was underway.

Space - textSectionComponent

                                         